Third-party reviewer speeds up building permit approval process in California

https://journal.firsttuesday.us/wp-content/uploads/Audio-LW_523.mp3

Why this matters: Homebuilders now have the option to hire their own licensed engineers or architects to approve building plans when a local agency takes longer than 30 days to approve the plans.

California legislature streamlines building obstacles

California is experiencing a severe housing shortage. Delays in approving building standards for new construction work against the state’s need to build more housing, faster.

With Assembly Bill (AB) 253, residential homebuilders may hire a licensed third-party reviewer to review building plans when a local building department takes more than 30 days to approve a building plan. The third-party reviewer is a professional licensed engineer or architect who holds no financial interest in the residential building permit.

A homebuilder who chooses to hire a third-party reviewer to perform the plan check notifies the city or county no later than five business days after:

the city or county provides an estimated timeframe for determining compliance with building standards that exceeds 30 business days; or30 business days have passed since the building permit application was deemed complete without the city or county determining compliance with building standards. [Calif. Health and Safety Code §17960.3(b)]

When the third-party reviewer checks the plans for building compliance, the third-party reviewer prepares an affidavit stating:

the plans do or do not comply with building requirements; andthe third-party reviewer performed the plan check. [Health & S C §17960.3(c)(1)]

The homebuilder submits a report to the city or county which includes:

the third-party reviewer’s affidavit;when the plans do not comply with building requirements as determined by the third-party reviewer, modifications to the plans that comply with building requirements; andadditional information required by the city or county. [Health & S C §17960.3(c)(2)]

After receiving the report, the city or county then has 10 business days to either:

issue the residential building permit; ornotify the homebuilder in writing that the plans do not comply, specifying the requirements for the plans to comply. [Health & S C §17960.3(c)(3)]

When the city or county does not issue the residential building permit or notify the homebuilder within 10 business days, and the affidavit provided by the third-party reviewer states the plans comply with building requirements and local ordinances, the residential building permit is deemed approved. [Health & S C §17960.3(c)(4)]

The law was declared an urgency statute and went into immediate effect October 10, 2025 when it was signed and sunsets January 1, 2036.

Related article:

Housing developments get approvals in 45 days, period

Get In Touch

Contact Us

If you’re ready to buy or sell your home, I’m here to serve you. Contact me directly with any questions—let’s get started!

    I agree to receive marketing and customer service calls and text messages from Handel Homes. Consent is not a condition of purchase. Msg/data rates may apply. Msg frequency varies. Reply STOP to unsubscribe. Privacy Policy & Terms of Service

    Skip to content